» Go to news mainSexton Construction Update ‑ Jan 4, 2017
Excavation activities on Sexton campus for the construction of two new buildings is nearing completion. Work on the Morris Street site for the Design Building will be complete Jan. 13, with work on
Innovation Site, next to C and C1, wrapping up by January 19.Â
The sidewalk on the north side of Morris Street is now closed and will shortly be relocated to the street where metered parking is currently. Many metered parking spots on the north side of Morris will be removed for the duration of construction. Until the sidewalk relocation is complete, everyone travelling on Morris Street is urged to cross to the south side at marked crosswalks.
Read full construction update here.Â
The IDEA Project is a transformational $64-million investment to мÓÆÂÁùºÏ²Ê¿ª½±Ö±²¥â€™s Engineering and Architecture campus and will be complete in spring 2018.Â
For full information on all ongoing renewal of Sexton Campus click here.
Recent News
- In Memoriam ‑ Colin Spinney
- Document delivery during Canada Post strike
- New surplus items added in Halifax
- Dal Tigers birthday parties
- Celebrate culture, creativity, and sustainability at the IEW Fashion Show!
- Student Accessibility Closure Friday, November 22
- Where suppliers can meet Dal Procurement
- LSC power outage Saturday, November 23